Tuesday, July 26, 2011

Broadband Resolution Passed at County Board Meeting

Today was a very full and productive day at the Courthouse.  The County Board met from 8:30 AM until approximately 4:30 PM today (less a lunch break).  Following is a summary of the day.

County Chair Jim Johnson and Commissioners Hakes,  Hall, Martinson and Sobanja were all present for today's regularly scheduled Board Meeting which included an evaluation presentation on Superior National Golf Course (SNGC) from Sirius Golf Advisors.

Open Forum
Richard Olson and Shawn Perich requested the County work with Hovland property owners to resolve flooding issues caused by the undersized culvert where Otis Creek crosses the Arrowhead Trail.  Otis Creek has overtopped the Arrowhead culvert five times over the past six years causing damage to private property.  County Engineer Dave Betts is aware of the problem and will prepare a plan to resolve this issue for presentation at the 8/16/11 County Board meeting.

Highway Department
County Engineer David Betts asked the Board to assign (2) Commissioners to the Facility Study Committee to assess the work on the Highway Department Master Site Plan being led by Oertel Architects. Commissioners Martinson and Sobanja will join the Committee of Maintenance Supervisor Russell Klegstad, Maintenance Department Head Brian Silence, Auditor-Treasurer Braidy Powers and Highway Department Accountant Anne Zellner.

Moose Habitat Collaborative Support Letter
Land Commissioner Mary Black requested the Board write a letter of support for the MN Moose Habitat Collaborative application for Lessard-Sams Outdoor Heritage Council funds to restore moose habitat in NE Minnesota.  The Board voted unanimously to join the MN Deer Hunters Association, Nature Conservancy, USFS, MN DNR, 1854 Authority, Grand Portage and Fon du Lac Bands of Lake Superior Chippewa, Lake and St. Louis Counties by providing a letter of support.

Office of Planning and Zoning (OPZ)
As recommended by the Planning Commission, the Board unanimously approved a zone change from Lakeshore Residential to Resort Commercial/Residential on property adjacent to Gunflint Lake and owned by John Schloot, dba Cross River Properties.

The Board denied a request for a Conditional User Permit to allow placement of a single family residence on a property owned by Joseph Sanders within the General Commercial zone district.  This request was denied for non-compliance with other zoning requirements 4-1 with Commissioner Sobanja dissenting.

The Board unanimously approved a request from Arrowhead Electric Cooperative for an Interim Use Permit to allow the temporary storage of fiber optic cable on property within the Lutsen Town Center Single Family Residential District.

Arrowhead Electric Cooperative Request for 1% Funds
Arrowhead Electric Cooperative (AEC) came before the County Board to request $4 million of 1% Local Option Sales Tax funding for their Broadband Project.  AEC has been awarded a combination grant and loan of $16 million through the federal Rural Utility Service for purposes of installing broadband technology throughout Cook County by making high speed internet available to all customers served by Arrowhead Electric and the Grand Marais Public Utilities Commission.  AEC is incurring at least $5.4 million in debt to undertake and complete the Broadband Project.  AEC needs an additional $4 million to ensure that the system is adequately robust, redundant, and long lasting.  The Board approved this request unanimously.

Capital Purchase Request
The Board authorized IS Director Danna MacKenzie to purchase (3) Dell computers as part of the IS Department's regularly planned rotation and maintenance plan as budgeted.

Community Center Project Update
Tom Wacholz of ORB Management informed the Board that sample collections (drilling) at the various Community Center site options will begin tomorrow, July 27.  The Board voted unanimously to add samples to be collected from the potential school site option.

ISD166 Superintendent Beth Schwarz updated the County Board on the School Board's two-part motion indicating the School District's willingness to consider a proposal that would attach the Community Center to the School District.  Advocates for attaching the Community Center to the School envision this to be at no-cost to ISD166 and should reduce annual operations and maintenance costs for the District.

The County Board discussed possible options to allow the City of Grand Marais to participate in the Cook County Community Center project.  Ultimately the Board passed a motion to suspend further Community Center design activities and expenses until the matter of the City's participation is resolved.  The contracts with ORB Management for Community Center Contract Management and Meyer Group for Community Center design will be suspended with the exception of the current site evaluation process.  The County will invite the City Council to a joint County/City work session on 8/23/11 to discuss the matter further.

Auditor-Treasurer
Auditor-Treasurer Braidy Powers asked the Board to approve a Public Hearing for Miscellaneous Fees.  The Hearing will be scheduled for 10 AM on August 23.  Powers also asked the Board to approve an extension to the Tait Lake Firewise Grant, which was approved.

Evaluation of Superior National Golf Course (SNGC) in Lutsen 
Sirius Golf Advisors President John Waite and Golf Course Architect Jeff Brauer presented their draft Evaluation of SNGC to the County Board and several members of the Public, including members of the EDA.  The final report will be available in approximately 2 weeks; no significant changes are anticipated.  An Executive Summary of the ~175 page document was also provided.

Overall response to the study and the presentation was very positive and well-received.  The County Board, as well as others in attendance asked clarifying questions of Waite and Brauer.  The report noted the original SNGC mission to spur economic development in the area and to bring more tourists into the area.  So, at this point, the most important question to be asked is whether or not the original mission statement for Superior National Golf Course is still valid.  Answering this question is critical to how the County Board and the EDA should move forward.  Sirius Golf Advisors offered (3) different scenarios for consideration, each requiring a different amount of funding.  The EDA and SNGC staff will explore possible funding sources in addition to their anticipated request for 1% Local Option Sales Tax funds.

Monday, July 18, 2011

Minnesota Public Radio's Broadband Coverage

Minnesota Public Radio (MPR) has been tracking seven places around Minnesota --and calling them Ground Level's Broadband 7 -- as these  (7) communities continue efforts to provide broadband services to their populations.  Cook County is one of those (7).

Read more at:

http://minnesota.publicradio.org/collections/special/columns/ground-level/archive/2011/07/broadband-7-revisited.shtml

For more specific information about the Arrowhead Electric Cooperative broadband project go to:

http://www.aecimn.com/

Thursday, July 14, 2011

Possible end to State Government shutdown

In a sincere effort to "stop the pain" caused by the MN State Government shutdown, Governor Dayton has made a move to drop his pursuit of tax hikes and accept a previously made Republican Party offer with some concessions. 

Read more at:  http://www.startribune.com/local/125567728.html

Wednesday, July 13, 2011

County Board Meeting

County Board Chair Jim Johnson and Commissioners Hakes, Hall, Martinson and Sobanja were all present for today's regular County Board Meeting.  Also present were Janet Simonen, Braidy Powers and Tim Scannell.

Public Comment
Hal Greenwood, Matt Hueltner, Gary Gamble, Evelyn Larson and Irene Thompson came before the County Board to present survey information from their "Stop the Madness" Campaign in opposition to the proposed Cook County Community Center.  Members of the County Board shared the group's concern about Operation and Maintenance Costs and re-stated their determination to build a facility that is financially sustainable without any increase to taxes.  Gamble said that their group wasn't always aware of the on-going decision making process; Hakes extended an invitation to attend any of the Steering Committee Meetings which are always open to the public.

PUBLIC HEARING
A Public Hearing was held to consider adopting proposed amendments to the Cook County Fiber Optic Network Ordinance.  The purpose of the Broadband Commission is "to advise and educate on the development, adoption , and use of broadband and directly related technologies".   The County Board approved this amendment which becomes effective upon publication.

Maintenance Department
Maintenance Director Brian Silence presented a quote to purchase a new County car for $21,197.  The Board passed a motion 4-1 approving this purchase with Commissioner Hakes opposed.  Hakes said she couldn't support the purchase without a clear understanding of the current fleet, associated costs, and alternatives to purchasing (lease, employee-owned cars, scheduling).

Highway Department
At County Engineer David Betts' recommendation, the Board approved the easement agreement with the Forest Service for the Junco Creek project and approved entering into an agreement with Midwest Trenchless Technologies to clean and televise the CSAH 12 storm sewer .  Betts and Maintenance Supervisor Russell Klegstad gave an overview of the on-going construction and maintenance projects noting that calcium chloride applications began 7/11/11 and should be complete this week.

Office of Planning and Zoning
Planning and Zoning Director Tim Nelson reminded the Board that the Poplar River Alternative Urban Area-wide Review (AUAR) which was initially adopted in June 2006 is up for renewal if it is to continue as an active environmental review document.  Nelson recommended the Board re-adopt the original AUAR document and mitigation plan for another five years as well as adopt by reference two additional studies that had been conducted in the Poplar River area and provide more recent information for review in conjunction with the mitigation plan.  After discussion, the Board approved the motion unanimously.

Nelson also reported the North Shore Management Board (NSMB) is considering whether or not to initiate another amendment process to the existing North Shore Management Plan.  The Board recommends no change to the Plan at this time.

Cook County Local Energy Project (CCLEP)
CCLEP is in need of a Staff person to increase their ability to carry out their mission.  George Wilkes, CCLEP Chair, requested the County Board provide $1000 in matching funds toward a 1/2 time Coordinator position to manage CCLEP activities.  CCLEP intends to apply to the Lloyd K. Johnson Foundation for the balance of $19,000.  Wilkes' request was approved by the Board.

AT&T Tower Leases
Mark Hemstereet of Insight (representing AT&T), Sheriff Mark Falk, and Duane Ege provided an update of the (2) new towers being considered for construction at Gunflint Magnetic and Gunflint Mid-Trail.  The logistics of building these towers is complex, but the general gist of it is that AT&T would pay for the construction of these towers.  In return for building the towers, any rents to be paid by AT&T would be abated for 25 years.  The estimated cost to build each tower is $200,000.  The County will have full ownership of these towers and retain the right to all rental income from both the current towers and the new towers.

Schroeder Township Survey
Citizen petition votes have been tallied at 67% in favor of the corner restoration survey in Sections 7-8-9-17-19 T58N R5W.  A letter is forthcoming to all landowners in those sections and a Public Hearing has been scheduled for August 9 at 10 AM at the Cook County Courthouse.  For questions about this process or the survey, contact Cook County Surveyor Wayne Hensche at 387-1172 or County Auditor-Treasurer Braidy Powers at 387-3646.

Budget Calendar and State Shutdown
Department Heads are working on their 2012 Budgets for submission to Braidy Powers by July 29. 

The negative impact of the State Shutdown grows as the Shutdown continues.  Department Heads and the County Board are working to continue the provision of County Services in the least disruptive manner within the budget constraints and unknowns.

One Percent Project
Commissioner Sobanja reported that construction of the Library Addition project is going well.

The County Board discussed a letter received from the Cook County Community Center Board of Trustees regarding the benefits of attaching the proposed Community Center to ISD166.  Beth Schwarz was present for this discussion and took the action to meet with the School Board to determine their interest and willingness to explore this option further.  The next Steering Committee Meeting is slated for July 27.

NE MN Area Transportation Partnership (NMATP)
Lutsen Township Supervisor, Diane Parker, applied for the position of Cook County Rep to the NMATP.   The Board approved this unanimously.




 

Saturday, July 2, 2011

Tuesday, June 28, 2011

More on the Possible State Government Shutdown...

Uncertainty about the potential State Government Shutdown still looms.  The County Board and County Staff are hopeful an agreement between the legislature and the governor on the FY 12-13 budget will be achieved.

We did learn today that MN Supreme Court Chief Justice, Lorie S. Gildea, in an email to judges and court employees said a petition filed in Ramsey District Court seeking continued funding for the courts (in the event their appropriation for FY12-13 is NOT approved by July 1) was granted.  This court order enables the operation of the court system in Cook County and throughout MN.

County Board Meeting and Preliminary Budget Worksession

County Board Vice-Chair Jan Hall ran today's County Board Meeting in Chair Jim Johnson's absence.  Commissioners Hakes, Martinson and Sobanja were all present.

Open Forum
No member of the Public opted to speak at today's Open Forum.

County Highway Department
On June 17, 2011 the Cook County Highway Department received five proposals in response to their Request for Proposals (RFP) for a Highway Department Facility Study and Master Site Plan.  County Engineer David Betts informed the County Board that the review committee for this project met, scored all (5) proposals, and recommends Oertel Architects/Albertson Engineering for the work.  The County Board authorized Betts and the County Attorney to negotiate a contract for this work not-to-exceed $25,300.

Betts, along with support from Anne Zellner and Russell Klegstad, presented the "2010 Annual Report of the Cook County Highway Department".  Highlights of the report included personnel changes and finances.  It also included summaries of 2010 construction & maintenance programs, gravel crushing, snowplowing, calcium chloride application, pavement and aggregate road surface improvements, and culvert projects.

Betts also reported the Highway Department will be negatively affected by a Government Shutdown, should that occur.  The Highway Department has (3) projects started or scheduled to start in July.  These projects will require QA Inspections and Independent Assurance tests which are typically done by MN DOT.  Betts is working to find acceptable alternatives for this testing to avoid delays in the projects for CSAH 8, Junco Creek Crossing and striping. 

Fiber Optic Network Commission
Since the FON Commission was created in 2009, efforts to build broadband infrastructure in Cook County have moved from the County to North East Service Cooperative and Arrowhead Electric Cooperative.  Because of this, the activities of the Commission have shifted from preparing to run a telecom business to monitoring, advising, educating, and assisting to ensure broadband infrastructure is built, that it meets the needs of the County and its citizens, and that we have the skills and knowledge to leverage broadband-based technologies once they arrive.  Howard Hedstrom, Chair of the Fiber Optic Network (FON) Commission, with support from IS Director Danna MacKenzie requested the County Board review and accept the FON Commission recommended language to reflect these changes in the Ordinance.  The Board approved this change and a public hearing is scheduled for July 12 at 8:35 am to officially adopt the recommended amendments.

Cook County Visitor's Bureau (CCEVB)
Sally Nankivell, Executive Director of the CCEVB, presented the CCEVB Income and Expenses for FY 2010-11.  She also asked the County Board to approve the CCEVB Budget for FY 2011-2012.  The County Board acknowledged the accomplishments of the CCEVB and approved the Budget unanimously.

Cook County Board of Equalization
The County Board recessed the Board of Commissioner meeting and reconvened the 2011 County Board of Equalization meeting in which they accepted the recommendation of County Assessor Mary Black for adjustments in the Estimated Market Values for (2) west end properties.  Afterward, the County Board of Equalization was adjourned and the County Board of Commissioner's meeting was reconvened.

1% Sales Tax Projects--Community Center
Commissioner Hakes reported on the last meeting of the Community Center Steering Committee to note that they continued their in depth review of site options.  Hakes said that David Demmer of the Office and Planning & Zoning attended that meeting to inform the Committee about the process for delineating wetlands in the NW Corner for possible building of a softball field or the Community Center Building. 

WORKSESSION re:  Cook County Finances/Budgets/Priorities
The County Board, along with County Auditor-Treasurer Braidy Powers, County Attorney Tim Scannell, Sheriff Mark Falk, and several Department Heads and Supervisors (Simonen, Futterer, Nelson, Betts, Klegstad, Booth) discussed the 2011 Budget Process.  Clearly, the Department Heads are looking for feedback and guidelines from the County Board in setting their budgets for the coming year.  Guidance from the County Board is especially important with a pending State Government shutdown as well as the on-going constraints on the County Budget including potential reductions in revenue, levy limits, increased costs, increasing demand for services, etc.  It was agreed that the County Board would gather input from the various departments and meet again to discuss this in a Special Meeting of the County Board at 10 AM on Friday July 8.